ALFAGEN – D.02 NOVÁ HALA TAO

Construsoftbimawards - ALFAGEN – D.02 NOVÁ HALA TAO
Category Industrial Projects
Year 2026
Country Czech Republic
Organization STAT-KON, s.r.o.
Project partners De Bondt, s.r.o.
Author HUTNÍ PROJEKT FRÝDEK MÍSTEK
Client INGSTEEL
Place of construction Areál AL INVEST Břidličná, a.s.
Tags Tekla StructuresTrimble ConnectSteel

Nová hala TaO je umiestnená v priestore odstránených objektov uhoľne, kotolne a spaľovne v areáli
AL INVEST Břidličná, a.s. má nepravidelný, členitý obdĺžnikový pôdorys s maximálnymi vonkajšími
rozmermi cca 285,68 x 67,58 m so zastavanou plochou 13 950,8 m² a objemom 26 727,8 m³.

Budova je nepodpivničená s jedným nadzemným podlažím, pričom obsahuje poschodové vstavby na
úrovniach +5,200 m, +6,000 m a +8,000 m, ktoré budú riešené v ďalšej fáze projektu, prístupné
vnútornými oceľovými schodiskami a plošinami v príslušných úrovniach. Budova je zastrešená súborom
pultových a sedlových striech so spádom 10 % s najvyššou výškou hrebeňa cca 19,28 m od
projektovej nuly, ktorou je podlaha haly a v rovnakej úrovni priľahlý upravený terén. Krytina je
asfaltová, na minerálnej izolácii na trapézovom plechu.

Z materiálového hľadiska ide o oceľový skelet opláštený ľahkým obvodovým plášťom –
sendvičovým panelom s minerálnym jadrom kladeným horizontálne – povrch tvorí profilovaný oceľový
plech – exteriér v sivej farbe RAL 9007, interiér v bielej farbe RAL 9010 a kazetovou stenou
zloženou z kaziet, minerálnej izolácie a trapézového plechu kladeného vertikálne v sivom farebnom
prevedení, farbe RAL 9007.

The new TaO hall is located on the site of the removed coal storage, boiler house, and incinerator facilities within the AL INVEST Břidličná, a.s. complex. It features an irregular, structured rectangular footprint with maximum external dimensions of approximately 285.68 x 67.58 m, a built-up area of 13,950.8 m², and a volume of 26,727.8 m³.

The building has no basement and consists of one above-ground floor, including multi-level internal structures (built-ins) at levels +5.200 m, +6,000 m, and +8,000 m. These will be addressed in a subsequent phase of the project and will be accessible via internal steel staircases and platforms at the respective levels. The building is covered by a series of mono-pitched and gable roofs with a 10% slope, with a maximum ridge height of approximately 19.28 m from the project zero point (defined as the hall floor level and the adjacent finished grade). The roofing consists of asphalt membranes over mineral insulation on trapezoidal steel sheeting.

Material-wise, the structure is a steel skeleton clad with a lightweight curtain wall – horizontally laid sandwich panels with a mineral core. The surface consists of profiled steel sheeting: the exterior in grey RAL 9007 and the interior in white RAL 9010. It also features a cassette wall system composed of cassettes, mineral insulation, and vertically laid trapezoidal sheeting in a grey finish, color RAL 9007.

Leave your comment

1 Comment
Newest
Oldest Most Voted
Inline Feedbacks
View all comments
14 days ago

Na tomto projekte naša spoločnosť STAT-KON spracovala výrobnú dokumentáciu pre spoločnosť Ingsteel. Základná geometria bola navrhnutá a namodelovaná spoločnosťou Hutní projekt Frýdek Místek. Chel by som oceniť kavalitný import z konkurenčného softwaru, ktorý nám veľmi uľahčil prácu. Aj toto vnímam ako predosť Tekly Sutructures. Poďakovanie patrí aj spoločnosti DeBondt s ktorou sme na výrobnej dokumentácii spolupracovali.